Marine Corps Base Camp Pendleton

Construction Projects

Camp Pendleton Map 

Recruit Barracks -Constructs four story open bay BEQ for SOI with a parking for 330 vehicles. The facility will have arms rooms, laundry rooms, and company offices. Single Marine and Sailor Center - Building includes laundry facilities, multipurpose rooms, lounges, internet resource center, game rooms, meeting area, administrative offices,  housekeeping areas, and public restrooms. Las Pulgas Landfill - Remove 250,000CY of trash, removal of the existing liner and leachate collection system, and installation of a new prescriptive liner. Recon BN Operations complex - Constructs 185,000SF complex including a high-rise multi-story HQ and classroom, warehouse,  comm/elect maintenance shop, auto shop, paraloft, fitness center, fire station, location exchange, single marine center, post office, armory and parking garage. ANGLICO - Constructs HQ facility, armory, comm/elect maintenance shop, vehicle maintenance shop, and renovations to the existing facility for warehouse and applied instruction space. Truck Company - Constructs 55,080SF complex including Company Headquarters, Warehouse, Dispatch, Armory, Single Marine Facility, and a Dining Facility. This project also renovates the existing Vehicle Maintenance Facility and adds a 2,160 SF Maintenance Bay. Recon BN Operations complex construction. Enlisted dining facility - Constructs a 56,000SF consolidated dining facility with separate dining and serving areas for permanent party personnel and recruits. Recruit barracks - Constructs 24 K-span type structures in Ranges 501 and 505 to function as recruit field barracks to support manpower increases. BEQ - Construct one 233 room and one 200 room BEQs. Repair and alter brig building - Convert existing Brig Building to a Pre-trial Confinement facility for approximately 100 detainees. Constructs enlisted dining facility with drive-through and parking garage. CNAT/FRS Aviation Training and BEQ - Constructs a Center for Naval Aviation Technical Training (CNATT) Complex comprised of high-rise applied instruction center and multi-story administrative facility. Repair Serra Mesa Housing Electrical Distribution System - Constructs underground electrical system at Serra Mesa Housing. Repair Serra Mesa Housing Electrical Distribution System - Constructs underground electrical system at Serra Mesa Housing. New Naval Hospital - state-of-the-art with over 1,000 clinical spaces and 2,500 parking spots including a parking garage. New Naval Hospital - state-of-the-art with over 1,000 clinical spaces and 2,500 parking spots including a parking garage. Wire Mountain Road and Vandegrift Boulevard Interchange - Constructs a cloverleaf intersection at Vandegrift Blvd. and Wire Mountain Road.  Includes removal of existing traffic light and construction of a bridge overpass connecting I-5 overpass from Del Mar to South Mesa Housing. Wire Mountain Road and Vandegrift Boulevard Interchange - Constructs a cloverleaf intersection at Vandegrift Blvd. and Wire Mountain Road.  Includes removal of existing traffic light and construction of a bridge overpass connecting I-5 overpass from Del Mar to South Mesa Housing.
Construction Projects Details
Utilities Projects:
Project Name Project Description Community Impact Projected Date for Completion
Base-wide Communications Upgrade Fiber Optic & Telephone Install nearly 300,000LF of inter-camp and intra-camp Fiber Optic (FO) cable and telephone cable connectivity.  All intra-camp distribution will be underground in concrete encased conduits and manholes Road work throughout Mainside with traffic impacts including lane closures.  MACS Rd will have intermittent road closures Feb.2013 - June 2013. Cable installation along Basilone and San Mateo with intermittent traffic handling and detours. January 2014
Base-wide Electrical Distribution Upgrade  Project replaces the existing 12 kV Electrical Distribution System and subsystem with 8 new 12 kV circuits that provide approximately 60% of Base electrical power  Pole line construction and outages in the following areas (Oct. 2012-Oct. 2013): 22, 26, 11, 15, 27, 23.  Anticipate construction traffic in and around Mainside and 22 Areas. January 2014
Electrical Upgrades Constructs a 69KV electrical transmission system to provide efficient electrical distribution throughout Base. Constructs 4 new substations Pole line installation from 53 to 51 Area; anticipate traffic control and delays.  Heavy construction taking place in 51 Area near Chaisson Rd/Basilone intersection. Fall 2013
Advanced Water Treatment (Reverse Osmosis) Plant Constructs advanced water treatment facilities at the existing MCB Iron/Manganese (I/M) Water Treatment Plant   AWT is and running. Work at Del Mar Beach to conclude by beginning of April 2013.  Summer 2013
Advanced Water Treatment (Reverse Osmosis) Plant Constructs advanced water treatment facilities for the north water distribution system.  Anticipated lane closure on Basilone from 51 to 52 Areas and along Frontage Rd. from SONGS to Campground in 2014. January 2016
Water Conveyance Pipeline Constructs 25 miles of pipeline in conjuction with P1044 to distribution around northern areas of the distribution system.  Construction dust and debris on Basilone, El Camino Real, Las Pulgas, Stuart Mesa. Traffic impacts to begin Summer 2013.  Spring 2016
(11-16) Mainside Projects:
Project Name Project Description Community Impact Projected Date for Completion
Repair Serra Mesa Housing Electrical Distribution System Constructs underground electrical system at Serra Mesa Housing.  Impacts to electrical service intermittent, estimated to begin Spring 2013.  Fall 2013
(20) Main Gate Construction Projects:
Project Name Project Description Community Impact Projected Date for Completion
New Naval Hospital Constructs new state-of-the-art Naval Hospital with over 1,000 clinical spaces and 2,500 parking spots including a parking garage Increased construction traffic in Main Gate Area Spring 2014
Wire Mountain Road and Vandegrift Boulevard Interchange Constructs a cloverleaf intersection at Vandegrift Blvd. and Wire Mountain Road.  Includes removal of existing traffic light and construction of a bridge overpass connecting I-5 overpass from Del Mar to South Mesa Housing Road work along Vandegrift Blvd and Wire Mountain.  Traffic delays during phases of construction. Fall 2013
Southern Region Tertiary Treatment Plant Expansion (SRTTP) Expands the capacity of existing Southern Region Tertiary Treatment Plant  Construction taking place in 20 area; anticipate traffic near the commissary and through Vandergrift gate.   Spring 2014
(22) Chappo Projects:
Project Name Project Description Community Impact Projected Date for Completion
CNAT/FRS Aviation Training Facility and BEQ Constructs a Center for Naval Aviation Technical Training (CNATT) Complex comprised of high-rise applied instruction center and multi-story administrative facility Increase of dust in and around the project site and increased construction traffic in Chappo Area. Spring 2014
Enlisted Dining Facility Constructs enlisted dining facility with drive-through and parking garage Parking garage is now open for use. Parade Deck use impacted by sounds of construction.  Summer 2013
24 Area Projects:
Project Name Project Description Community Impact Projected Date for Completion
Bachelor Enlisted Quarters Construct one 233 room and one 200 room BEQs Road work along Vandegrift from 22 to 24 Area and throughout 24 Area.  Increased construction traffic in Pico Area. Spring 2014
Repair and Alter Brig Building Convert existing Brig Building to a Pre-trial Confinement facility for approximately 100 detainees Limited access to Brig. Summer 2013
(31A) Edson Range Projects:
Project Name Project Description Community Impact Projected Date for Completion
Recruit Barracks, Field/K-Span Constructs 24 K-span type structures in Ranges 501 and 505 to function as recruit field barracks to support manpower increases No public access.  Summer 2013
Enlisted Dining Facility Constructs a 56,000SF consolidated dining facility with separate dining and serving areas for permanent party personnel and recruits Increased traffic in 31 Area. Impacts to pedestrian walkways near existing mess hall.  Summer 2013
(33) Santa Margarita Projects:
Project Name Project Description Community Impact Projected Date for Completion
Truck Company Constructs 55,080SF complex including Company Headquarters, Warehouse, Dispatch, Armory, Single Marine Facility, and a Dining Facility. This project also renovates the existing Vehicle Maintenance Facility and adds a 2,160 SF Maintenance Bay. Increased construction traffic in Margarita Area. Intermittent road closures and various outages. February 2014
Recon Bn Operations Complex At MCB Camp Pendleton Margarita (33) Area Increased construction traffic in Margarita Area. Summer 2013
(41) Las Flores Projects:
Project Name Project Description Community Impact Projected Date for Completion
Recon Bn Operations Complex Constructs 185,000SF complex including a high-rise multi-story HQ and classroom, warehouse,  comm/elect maintenance shop, auto shop, paraloft, fitness center, fire station, location exchange, single marine center, post office, armory and parking garage El Camino Real/Stuart Mesa NB traffic delays until Winter 2013 for intersection realignment. Increased construction traffic in Las Pulgas. Intermittent outages throughout project duration. Summer 2013
ANGLICO Constructs HQ facility, armory, comm/elect maintenance shop, vehicle maintenance shop, and renovations to the existing facility for warehouse and applied instruction space El Camino Real/Stuart Mesa SB traffic delays until Winter 2013 for intersection realignment. Increased construction traffic in Las Pulgas. Intermittent outages throughout project duration. Summer 2013
(43) Pulgas Projects:
Project Name Project Description Community Impact Projected Date for Completion
Phase 1 Las Pulgas Landfill Remove 250,000CY of trash, removal of the existing liner and leachate collection system, and installation of a new prescriptive liner   Increased traffic on Basilone.  Work to commence Spring 2013.  Summer 2013
(52) SOI Projects:
Project Name Project Description Community Impact Projected Date for Completion
Recruit Barracks, School of Infantry Constructs four story open bay BEQ for SOI with a parking for 330 vehicles. The facility will have arms rooms, laundry rooms, and company offices Increased traffic through San Onofre and Las Pulgas Gates and along Basilone to 52 Area.  Parking limited in and around Barracks at SOI. February 2013
Single Marine and Sailor Center Building includes laundry facilities, multipurpose rooms, lounges, internet resource center, game rooms, meeting area, administrative offices,  housekeeping areas, and public restrooms Increased traffic through San Onofre and Las Pulgas Gates and along Basilone to 52 Area.  Construction site boarders Basilone Rd; expect slow traffic near the site. Summer 2013
Northern Region Tertiary Treatment Plant Expansion (NRTTP) Constructs North Regional Tertiary treatment plant and sludge treatment facility to treat raw sewage from tributary areas  Conveyance line installation along San Mateo Road between 62 Area and 52 Area.  NRTTP construction site between 51 and 52 Area; expect construction traffic along Basilone from Las Pulgas and San Onofre Gates. Spring 2014