| Utilities Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Base-wide Communications Upgrade Fiber Optic & Telephone |
Install nearly 300,000LF of inter-camp and intra-camp Fiber Optic (FO) cable and telephone cable connectivity. All intra-camp distribution will be underground in concrete encased conduits and manholes |
Road work throughout Mainside with traffic impacts including lane closures. MACS Rd will have intermittent road closures Feb.2013 - June 2013. Cable installation along Basilone and San Mateo with intermittent traffic handling and detours. |
January 2014 |
| Base-wide Electrical Distribution Upgrade |
Project replaces the existing 12 kV Electrical Distribution System and subsystem with 8 new 12 kV circuits that provide approximately 60% of Base electrical power |
Pole line construction and outages in the following areas (Oct. 2012-Oct. 2013): 22, 26, 11, 15, 27, 23. Anticipate construction traffic in and around Mainside and 22 Areas. |
January 2014 |
| Electrical Upgrades |
Constructs a 69KV electrical transmission system to provide efficient electrical distribution throughout Base. Constructs 4 new substations |
Pole line installation from 53 to 51 Area; anticipate traffic control and delays. Heavy construction taking place in 51 Area near Chaisson Rd/Basilone intersection. |
Fall 2013 |
| Advanced Water Treatment (Reverse Osmosis) Plant |
Constructs advanced water treatment facilities at the existing MCB Iron/Manganese (I/M) Water Treatment Plant |
AWT is and running. Work at Del Mar Beach to conclude by beginning of April 2013. |
Summer 2013 |
| Advanced Water Treatment (Reverse Osmosis) Plant |
Constructs advanced water treatment facilities for the north water distribution system. |
Anticipated lane closure on Basilone from 51 to 52 Areas and along Frontage Rd. from SONGS to Campground in 2014. |
January 2016 |
| Water Conveyance Pipeline |
Constructs 25 miles of pipeline in conjuction with P1044 to distribution around northern areas of the distribution system. |
Construction dust and debris on Basilone, El Camino Real, Las Pulgas, Stuart Mesa. Traffic impacts to begin Summer 2013. |
Spring 2016 |
|
|
|
|
| (11-16) Mainside Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Repair Serra Mesa Housing Electrical Distribution System |
Constructs underground electrical system at Serra Mesa Housing. |
Impacts to electrical service intermittent, estimated to begin Spring 2013. |
Fall 2013 |
|
|
|
|
| (20) Main Gate Construction Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| New Naval Hospital |
Constructs new state-of-the-art Naval Hospital with over 1,000 clinical spaces and 2,500 parking spots including a parking garage |
Increased construction traffic in Main Gate Area |
Spring 2014 |
| Wire Mountain Road and Vandegrift Boulevard Interchange |
Constructs a cloverleaf intersection at Vandegrift Blvd. and Wire Mountain Road. Includes removal of existing traffic light and construction of a bridge overpass connecting I-5 overpass from Del Mar to South Mesa Housing |
Road work along Vandegrift Blvd and Wire Mountain. Traffic delays during phases of construction. |
Fall 2013 |
| Southern Region Tertiary Treatment Plant Expansion (SRTTP) |
Expands the capacity of existing Southern Region Tertiary Treatment Plant |
Construction taking place in 20 area; anticipate traffic near the commissary and through Vandergrift gate. |
Spring 2014 |
|
|
|
|
| (22) Chappo Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| CNAT/FRS Aviation Training Facility and BEQ |
Constructs a Center for Naval Aviation Technical Training (CNATT) Complex comprised of high-rise applied instruction center and multi-story administrative facility |
Increase of dust in and around the project site and increased construction traffic in Chappo Area. |
Spring 2014 |
| Enlisted Dining Facility |
Constructs enlisted dining facility with drive-through and parking garage |
Parking garage is now open for use. Parade Deck use impacted by sounds of construction. |
Summer 2013 |
|
|
|
|
| 24 Area Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Bachelor Enlisted Quarters |
Construct one 233 room and one 200 room BEQs |
Road work along Vandegrift from 22 to 24 Area and throughout 24 Area. Increased construction traffic in Pico Area. |
Spring 2014 |
| Repair and Alter Brig Building |
Convert existing Brig Building to a Pre-trial Confinement facility for approximately 100 detainees |
Limited access to Brig. |
Summer 2013 |
|
|
|
|
| (31A) Edson Range Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Recruit Barracks, Field/K-Span |
Constructs 24 K-span type structures in Ranges 501 and 505 to function as recruit field barracks to support manpower increases |
No public access. |
Summer 2013 |
| Enlisted Dining Facility |
Constructs a 56,000SF consolidated dining facility with separate dining and serving areas for permanent party personnel and recruits |
Increased traffic in 31 Area. Impacts to pedestrian walkways near existing mess hall. |
Summer 2013 |
|
|
|
|
| (33) Santa Margarita Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Truck Company |
Constructs 55,080SF complex including Company Headquarters, Warehouse, Dispatch, Armory, Single Marine Facility, and a Dining Facility. This project also renovates the existing Vehicle Maintenance Facility and adds a 2,160 SF Maintenance Bay. |
Increased construction traffic in Margarita Area. Intermittent road closures and various outages. |
February 2014 |
| Recon Bn Operations Complex |
At MCB Camp Pendleton Margarita (33) Area |
Increased construction traffic in Margarita Area. |
Summer 2013 |
|
|
|
|
| (41) Las Flores Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Recon Bn Operations Complex |
Constructs 185,000SF complex including a high-rise multi-story HQ and classroom, warehouse, comm/elect maintenance shop, auto shop, paraloft, fitness center, fire station, location exchange, single marine center, post office, armory and parking garage |
El Camino Real/Stuart Mesa NB traffic delays until Winter 2013 for intersection realignment. Increased construction traffic in Las Pulgas. Intermittent outages throughout project duration. |
Summer 2013 |
| ANGLICO |
Constructs HQ facility, armory, comm/elect maintenance shop, vehicle maintenance shop, and renovations to the existing facility for warehouse and applied instruction space |
El Camino Real/Stuart Mesa SB traffic delays until Winter 2013 for intersection realignment. Increased construction traffic in Las Pulgas. Intermittent outages throughout project duration. |
Summer 2013 |
|
|
|
|
| (43) Pulgas Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Phase 1 Las Pulgas Landfill |
Remove 250,000CY of trash, removal of the existing liner and leachate collection system, and installation of a new prescriptive liner |
Increased traffic on Basilone. Work to commence Spring 2013. |
Summer 2013 |
|
|
|
|
| (52) SOI Projects: |
|
|
|
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Recruit Barracks, School of Infantry |
Constructs four story open bay BEQ for SOI with a parking for 330 vehicles. The facility will have arms rooms, laundry rooms, and company offices |
Increased traffic through San Onofre and Las Pulgas Gates and along Basilone to 52 Area. Parking limited in and around Barracks at SOI. |
February 2013 |
| Single Marine and Sailor Center |
Building includes laundry facilities, multipurpose rooms, lounges, internet resource center, game rooms, meeting area, administrative offices, housekeeping areas, and public restrooms |
Increased traffic through San Onofre and Las Pulgas Gates and along Basilone to 52 Area. Construction site boarders Basilone Rd; expect slow traffic near the site. |
Summer 2013 |
| Northern Region Tertiary Treatment Plant Expansion (NRTTP) |
Constructs North Regional Tertiary treatment plant and sludge treatment facility to treat raw sewage from tributary areas |
Conveyance line installation along San Mateo Road between 62 Area and 52 Area. NRTTP construction site between 51 and 52 Area; expect construction traffic along Basilone from Las Pulgas and San Onofre Gates. |
Spring 2014 |